IBM Cloud Docs
Site access requirements

Site access requirements


IBM Power Virtual Server Private Cloud: On-premises


Site planners can use this information to assess the physical site and operational requirements that are necessary to prepare your site for new IBM® Power® Virtual Server racks. Work with the IBM representative to ensure that these prerequisites are completed before the pods are delivered to your data center.

Review the following requirements that your IBM Power Virtual Server (On-premises) site must fulfill:

  • Accommodate a fully configured 42U rack that is 7 ft tall.
  • Provide secured and controlled access to the Power Virtual Server racks in your IBM Power Virtual Server (On-premises) site.
  • Provide the flooring that supports the weight of the Power Virtual Server racks.

Refer Table 1 to understand rack dimensions and weight.

Table 1. Rack dimensions and weight
Rack Width Depth Height Weight(Empty)
Rack only 600 mm (23.6 in.) 1070 mm (42.1 in.) 2020 mm (79.5 in.) 166 kg (365 lb)
Rack with two standard doors 600 mm (23.6 in.) 1132 mm (44.6 in) 2020 mm (79.5 in.) 177 kg (391 lb)
Rack with rear door, heat exchanger (dry), and standard doors 600 mm (23.6 in.) 1231 mm (48.5 in.) 2020 mm (79.5 in.) 210 kg (463 lb)
Rack with high-end appearance front door and rear door 600 mm (23.6 in.) 1210 mm (47.3 in.) 2020 mm (79.5 in.) 181 kg (398 lb)

Refer to Table 2 to understand rack characteristics and capacity.

Table 2. Rack characteristics and capacity
Characteristics Maximum weight EIA unit capacity
Dynamic (rolling) 1134 kg (2500 lb) 18 kg (40 lb) or EIA average
Static 1678 kg (3700 lb) 32 kg (70 lb) or EIA average
Seismic certified 1170 mm (2580 lb) 20 kg (45 lb) or EIA maximum
EIA: Energy Information Administration

Floor load calculator: You can use Floor load calculator to determine the distributed load that a server, expansion unit, or migration tower places on a subfloor (for example, in a data center with a raised floor) or on an above-ground or nonraised floor structure.

For generic prerequisites and planning guidelines for Power10, see the following topics: